Section 1397. Risk of work before delivery
Act no. none printed (index gives 0)1867In forceGoa (State Act)
Article 1397 – Risk of work before delivery - Where the contractor, or contractors bind themselves to supply the labour and materials, all the risk of the work shall be borne by the contractors until its delivery, unless the delivery is delayed by failure of the owner to accept it or unless otherwise expressly provided.