State Act

24

Section 24. Limitation of claims.

The Telangana Irrigation Act, 1357 Fasli.

Act no. 24 of 1357 F.1357In forceTelangana (State Act)

24. No claim for compensation under this Act made after the expiration of a period of one year from the date when the alleged damage occured shall be entertained unless the Collector is satisfied that the claimant had sufficient cause for not making the claim within such period.